Client NameThe School District of Millburn
Bids Due/Opening*Postponed - New Bid opening date is:
Friday, March 9, 2018 at the Millburn Board of Education Office at 434 Millburn Avenue, Millburn, NJ 07041
Pre-Bid Walk ThroughWednesday, February 14th, 2018 11:00 AM Located at the Main Office of Millburn High School
462 Millburn Ave, Millburn, NJ 07041
Project # & NamePSA#(s) 6793HS: Millburn High School – Media Center Addition and Renovations for New Maker Space
Cost of Documents$125.00 Non-Refundable.
Bidding documents will be released only in full sets. Partial sets, or sets split out by trade will not be released. Bid Documents may be delivered to recipients at their request upon our receipt of fee and arrangements for payment of delivery.
Project ArchitectRachel Tiedemann
Drawings AvailableWednesday, January 24th, 2018 at the offices of Parette Somjen Architects L.L.C.
Drawings will be available for contractor review Monday - Thursday from 9:00am - 4:00 pm and Friday from 9:00am - 1:00 pm.
Bidding RequirementsBids will be accepted from a single general contractor for a lump sum bid only
Project DescriptionThe scope of work includes, but not limited to, renovation to convert an existing Media Center into Maker Space (STEM Lab) and construction of new one story Media Center with a connection to the existing building. The scope to renovate the Existing Media Center into a new Maker Space will involve building system modifications including electrical, sprinkler, mechanical, and limited plumbing. The new multipurpose addition will include approximately a one- story addition that will receive electrical, mechanical, and limited plumbing.

• Program: ± 8080 SF Alteration
± 2520 SF Alteration

• 1 New Media Center with attached Study/Storage Room and Stack Area

• Alterations in existing Media Center to convert to Maker Space:
- 1 New Common Area with Flexible Classroom Space
- 2 New Classrooms with Millwork
- 1 New Workroom
- 1 New Small Group Classroom with Storage
- 1 New MDF Closet
- 2 New Offices
- 1 New Storage Room

• Site Work:
- New open friction porous pavement driveway
- New concrete sidewalks
- New chain link fence with gates
- New doorway landings
- New sewage pump station
- Restoration of site
- New & reconstructed storm water drainage inlets
- New Hose Bib
• Roof:
- New Modified Bitumen roof at the addition with interior drainage (Garland)

• Structural:
- New steel structure for Addition
- New steel for operable partitions in existing building

• MEP
- Addition has exposed metal ductwork
- 1 New RTU at the Addition
- 1 New Ductless Split System in the renovated building
- Modified ductwork in the renovated building
- New sink with millwork in Maker Space
- New Fire Alarm Devices

• Finishes
- Terrazzo/Carpet/LVT/VCT Floor Finishes
- Acoustical Suspended ceilings
- New interior storefront systems (operable & fixed)
- New Fixed & projected windows to match existing
- New interior & exterior doors
- New operable felt wall
DPMC Qualification(C008) General Construction
(C009) General Construction / Alterations & Additions
(C029) Structural Steel & Ornamental Iron
(C030) Plumbing
(C032) HVACR
(C047) Electrical
Commence ConstructionSite Work: Monday, April 9th, 2018
Phase I – Renovation/Alteration: Thursday, April 12th, 2018
Phase II – Addition: Thursday, April 12th, 2018
Substantial CompletionPhase I – Alterations/Renovations: Thursday, August 16th, 2018
Phase II – Alterations/Renovations: Thursday, September 27th, 2018
Addendum Issued:
Bid Pickup List Bidder's List
Bid Results Bid Results