Project Number:

7458UMS

Rutherford Board of Education

Floor Replacement at Union School

Project Information:

Client:

Project Name:

Project Architect:

Project Description:

Rutherford Board of Education

Floor Replacement at Union School

Rachel Tiedemann

The scope of this project includes, but is not limited to, the repair of slab moisture infiltration in select classrooms throughout the building.​

  • Program:± 6,367 SF Renovation/Alteration

  • The repairs will require removing the existing flooring system down to the existing concrete slab on grade, and providing a new concrete topping slab, vapor reduction system, and floor finish.

  • Existing mechanical and electrical to be uninstalled / reinstalled as required to facilitate the removal of the existing flooring system and the installation of the new flooring system.

Bid Information:

DPMC Qualification:

Cost of Documents:

Bidding Requirements:

(C008) General Construction (C009) General Construction / Alterations & Additions

$25.00 Non-Refundable.

Bids will be accepted from a single general contractor for a lump sum bid only.

Schedule:

Drawings Available:

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Commence Construction:

Substantial Completion:

Thursday, February 6th, 2020

Wednesday, February 13th, 2020 at 3:00 PM, located at the Union Middle School 359 Union Avenue Rutherford, NJ 07070

Wednesday, March 4th, 2020, at 11:00 AM located at Rutherford BOE 176 Park Avenue Rutherford, NJ 07070

Wednesday, June 24th, 2020

Monday, August 24th, 2020