Project Number:

8213

Bloomfield Board of Education

Boiler Replacement at Berkeley Elementary School & Oak View Elementary School

Project Information:

Client:

Project Name:

Project Architect:

Project Description:

Bloomfield Board of Education

Boiler Replacement at Berkeley Elementary School & Oak View Elementary School

Jose Maria V. Rivera

Berkeley:
The scope of the project includes, but is not limited to, the replacement of two of three existing boilers with one new boiler. Work shall also include new piping, other associated equipment, and integration of controls. Existing boiler to remain must be operational throughout duration of project and maintain heat to the school building.


Oak View:
The scope of the project includes, but is not limited to, the replacement of one of the two existing boilers with new. Work shall also include new piping, other associated equipment, and integration of controls. Existing boiler to remain must be operational throughout duration of project and maintain heat to the school building.

Bid Information:

DPMC Qualification:

Cost of Documents:

Bidding Requirements:

(C032) HVACR or (C033) Boilers

$25.00 Non-Refundable.

Bids will be accepted from a single general contractor for a lump sum bid only.

Schedule:

Drawings Available:

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Commence Construction:

Substantial Completion:

Friday, February 21, 2020 at the offices of Parette Somjen Architects L.L.C. Drawings will be available for contractor review Monday - Friday from 9:00am - 4:00 pm and Friday from 9:00am - 1:00 pm.

Wednesday, February 26, 2020 at 03:30 PM. Meet at the Main Office of Berkeley Elementary School. Oak View to follow.

Tuesday, March 17, 2020 @ 10:00 AM at the Board Offices Located at 155 Broad Street, Bloomfield, NJ 07003

Friday, July 10, 2020 or when District shuts down heating.

Friday, September 18, 2020

Bidder's List: