Project Number:

8315

Bridgewater Raritan Regional Board of Education

Building 200 Roof Replacement at Bridgewater-Raritan High school

Project Information:

Client:

Project Name:

Project Architect:

Project Description:

Bridgewater Raritan Regional Board of Education

Building 200 Roof Replacement at Bridgewater-Raritan High school

David Didimamoff

The scope of the project includes, but is not limited to, the removal and replacement of the existing roofing system down to the roof deck with the installation of a new built-up roofing system at Building 200. There will be a new roofing membrane installed, new insulation, new roof drains and new metal edge coping, as well as various additional roofing components necessary for the installation of the new roof.

Bid Information:

DPMC Qualification:

Cost of Documents:

Bidding Requirements:

(C008) General Construction, (C009) General Construction / Alterations / Additions, (C068) Roofing Membrane Modified Bitumen, (C070) Roofing – Built Up

$25.00 Non-Refundable.

Bids will be accepted from a single general contractor for a lump sum bid only.

Schedule:

Drawings Available:

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Commence Construction:

Substantial Completion:

Friday, February 14, 2020 at the offices of Parette Somjen Architects L.L.C. Drawings will be available for contractor review Monday - Thursday from 9:00am - 4:00 pm and Friday from 9:00am - 1:00 pm.

Tuesday, February 18, 2020 at 3:00 PM

Thursday, March 05, 2020 @ 11:00 AM at the 836 Newmans Lane, Bridgewater, NJ 08807

Monday, June 22, 2020

Friday, August 21, 2020