The scope of the project includes, but is not limited to, the removal of ±15,550 sf of the existing roofing system located at the front portion of the school and replacement with a new build-up modified bituminous roofing system. Existing perimeter metal edgework, roof drains, and flashing to be replaced with new.

Bid Information:

DPMC Qualification:

Cost of Documents:

Bidding Requirements:

(C068) Roofing-Membrane Modified Bitumen; (C047) Electrical

$25.00 Non-Refundable.

Bids will be accepted from a single general contractor for a lump sum bid only.

Schedule:

Drawings Available:

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Commence Construction:

Substantial Completion:

Friday, February 21, 2020, at the offices of Parette Somjen Architects L.L.C. Drawings available for contractor review Monday – Friday from 9:00 am – 4:00 pm

Tuesday, February 25, 2020 at 11:00 am

Friday, February 28, 2020

Wednesday, March 11, 2020 at 12:30 pm

Monday, June 29, 2020

Friday, August 07, 2020