Project Number:
8366
Glen Rock BOE
RTU Replacement at Glen Rock High School & Middle School
Project Information:
Client:
Project Name:
Project Architect:
Project Description:
Glen Rock BOE
RTU Replacement at Glen Rock High School & Middle School
David Didimamoff
The scope of this project includes, but not limited to the removal of existing RTU #4 and replacing with two new RTUs to provide heating and cooling to the locker rooms, weight room, training room & ancillary support spaces. There are electrical upgrades to accommodate the installation of the new HVAC equipment and modification to the roof as needed.
Bid Information:
DPMC Qualification:
Cost of Documents:
Bidding Requirements:
(C032) HVACR
$25.00 Non-Refundable.
Bids will be accepted from a single general contractor for a lump sum bid only.
Schedule:
Drawings Available:
Pre-Bid Walkthrough:
Addendum:
Bids Due / Opening:
Commence Construction:
Substantial Completion:
Wednesday, 15 April 2020 via download from File Transfer Protocol (FTP)
website. Said bidding documents may be obtained by submitting a request to ddidimamoff@planetpsa.com. Bidding documents will not be mailed, emailed or available for pickup or inspection. They may only be downloaded from the
FTP website with access granted upon request. Bidders must email their
request at least twenty‐four (24) hours or one (1) business day in advance to gain access to bid documents.
Tuesday, 28 April 2020 @ 11:00 am at the Board Offices Located at
400 Hamilton Ave, Glen Rock, NJ 07452
Monday, 22 June 2020
Friday, 21 August 2020
Bidder's List: