Project Number:

8550

Andover Regional Board of Education

Partial Roof Replacement at Long Pond School

Project Information:

Client:

Project Name:

Project Architect:

Project Description:

Andover Regional Board of Education

Partial Roof Replacement at Long Pond School

Joshua Thompson

The scope of this project includes, but is not limited to, replacing roofing at the front of the school. The existing roof system will be removed down to sound substrate and a new modified bitumen multi-ply roofing system will be installed. Replace existing perimeter metal edge, roof drains, and flashing with new. Existing shingle roof at front canopy to be replaced with new.

Bid Information:

DPMC Qualification:

Cost of Documents:

Bidding Requirements:

(C068) Roofing Membrane Modified Bitumen

Specifications, proposal forms, etc. may be obtained on Friday, January 29, 2021 via download from FTP website. Said bidding documents may be obtained by submitting a request to lcamacho@planetpsa.com. Bidding documents will not be mailed, emailed, or available for pickup or inspection. They may only be downloaded from the secure FTP website with access granted upon request. Bidders must email their request at least twenty-four (24) hours or (1) business day in advance to gain access to bid documents.

Bids will be accepted from a single general contractor for a lump sum bid only.

Schedule:

Drawings Available:

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Commence Construction:

Substantial Completion:

Friday, January 29, 2021

Wednesday, February 03, 2021 at 2:00pm

Friday, February 05, 2021

Thursday, February 18, 2021 at 10:00 am

Monday, June 28, 2021

Friday, August 20, 2021