Project Number:
8606CS
Cranbury Township Boad of Education
Improvements and Additions at Cranbury School
Project Information:
Client:
Project Name:
Project Architect:
Project Description:
Cranbury Township Boad of Education
Improvements and Additions at Cranbury School
Hae-An Chyun
This project includes, but is not limited to
i. Renovation of the existing Public District Library into the Main Office and Academic commons
ii. Renovation of the existing gym/all-purpose room to performing arts.
iii. Full renovation of kitchen and cafeteria, includes new food service equipment and associated utility
upgrades, new finishes and doors, new furniture.
iv. Parking & sidewalk renovations
Bid Information:
DPMC Qualification:
(C008) General Construction or
(C009) General Construction / Alterations and
Additions
Cost of Documents:
$00.00 Non-Refundable.
Bidding documents will be released only in full sets. Partial sets, or sets
split out by trade will not be released. Bidding documents may be
obtained by submitting a request to Hae-An Chyun, AIA at
hchyun@planetpsa.com. Bidding documents will not be mailed, emailed
or available for pickup or inspection. They may only be downloaded
from the FTP website with access granted upon request. Bidders must
email their request at least twenty-four (24) hours or one (1) business
day in advance to gain access to bid documents.
Budget Cost Estimate:
$12-$14 Million
Bidding Requirements:
Bids will be accepted from a single general contractor for a lump sum bid only.
Schedule:
Drawings Available:
Friday, August 18, 2023 at the offices of Parette Somjen Architects
L.L.C.
Drawings will be available for contractor review Monday - Thursday
Pre-Bid Walkthrough:
Addendum:
Bids Due / Opening:
Wednesday, August 23, 2023 at 11:00AM
Friday, September 15, 2023 @ 2:00PM at the Board Offices Located at
23 North Main Street, Cranbury, NJ 08512
Commence Construction:
Substantial Completion:
November 6 – November 10, 2023: Phase 1A Abatement
(Existing Media Center)
-November 10, 2023 – June 17, 2024: Phase 1A Construction
(Academic Commons)
-June 17, 2024 – July 12, 2024: Phase 1B & 2 Abatement
(Auditorium/Nurse/Partial Main Office)
-June 17, 2024 – August 30, 2024: Phase 3A Abatement & Construction
(Kitchen/Cafeteria)
-June 17, 2024 – December 31, 2024: Phase 2 Construction
(Business Office/STEAM/Aquaponics)
-June 17, 2024 – August 29, 2025: Phase 1B Construction
(Auditorium)
-September 1, 2025
Bidder's List:
Bidders | Address | Telephone |
---|
Bidders | Address | Telephone |
---|