Project Number:

9175LVMS-HVAC

Washington Township BOE

HVAC Upgrades @ Long Valley Middle School

Project Information:

Client:

Project Name:

Project Lead:

Project Description:

Washington Township BOE

HVAC Upgrades @ Long Valley Middle School

Hae-An Chyun

The scope of the project includes but is not limited to HVAC Replacement.

Bid Information:

DPMC Qualification:

(C032) HVACR
(C029) STRUCTURAL STEEL AND ORNAMENTAL IRON
(C030) PLUMBING
(C047) ELECTRICAL

Cost of Documents:

Bidding Requirements:

Bids will be accepted from a single general contractor for a lump sum bid as follows:

Schedule:

Drawings Available:

Friday, October 11, 2024

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Tuesday, October 15, 2024 at 3:30pm at 51 West Mill Road, Long Valley, NJ 07853

Thursday, November 14, 2024 at 1:00pm at 53 West Mill Rd. Long Valley, NJ 07853

Commence Construction:

Substantial Completion:

Tuesday, June 17, 2025

Friday, August 22, 2025