Project Number:
10630
Summit Public Schools Board of Education
Generator Replacement at Lawton C. Johnson Middle School
Project Information:
Client:
Project Name:
Summit Public Schools Board of Education
Generator Replacement at Lawton C. Johnson Middle School
Project Contact:
Project Description:
Matt Binshtock
The scope of this project includes, but is not limited to, the replacement in kind of the existing 150kW Natural Gas Generator. In addition, the replacement of associated transfer switch, replace existing wiring within the conduits, replace existing concrete slab and repair fence where required.
Bidding Requirements:
Bids will be accepted from a single general contractor for a lump sum bid
Bidder Qualification:
(C008) GENERAL CONSTRUCTION
(C009) GENERAL CONSTRUCTION / ALTERATIONS / ADDITIONS
(C047) ELECTRICAL
Major Subcontractor:
(C047) ELECTRICAL
Specialty Subcontractor:
N/A
Schedule:
Drawings Available:
Pre-Bid Walkthrough:
Tuesday, October 6, 2026
Wednesday, October 14, 2026 at 1:00 PM at 272 Morris Ave, Summit, NJ 07901
Addendum:
Bids Due / Opening:
Tuesday, October 27, 2026
Thursday, November 5, 2026 at 1:00 PM at 14 Beekman Terrace, Summit, NJ 07901
Commence Construction:
Friday, November 13, 2026
Substantial Completion:
Wednesday, August 18, 2027
Bidder's List:
Bidders | Address | Telephone |
|---|---|---|
Bidders | Address | Telephone |
|---|---|---|